Market Assumptions |
Anticipated days/week of operation |
5 |
days |
Average # of tons required per day |
70 |
tons |
Off-road diesel fuel cost per gallon |
$ 4.28 |
per gallon |
Labor Cost per hour |
$ 50.00 |
|
Capital cost of Equipment |
$ 174,995 |
|
Input material per ton |
$ 6.00 |
|
Daily Operating Expense |
Hours of operation per day |
8.00 |
hours |
Labor |
$ 500.00 |
|
Input material |
$ 420.00 |
|
Fuel |
$ 321.00 |
|
Daily operating expense total |
$ 1,241.00 |
|
Total Cost per Ton of Recycled Asphalt |
Depreciation |
$ 1.83 |
Per ton |
Labor |
$ 7.14 |
Per ton |
Fuel |
$ 4.59 |
Per ton |
Input material |
$ 6.00 |
Per ton |
TOTAL PRODUCTION COST PER TON |
$ 19.56 |
|
Assumptions made for ROI Model
Operation: 5 days per week- 250 days per year operation
Labor- 8 hours per day production, 2 hours per day start-up/clean out
Rate is based on union operator- fully loaded hourly rate
Fuel- Additional 5 gallons factored into model for start-up/clean out
Capital cost- Bagela BA10000 Suggested Retail Price; 5-year straight line depreciation factor
Input material cost - market rate for tipping fee & cost of rejuvenating oil